9/27/18 Embassy of Rwanda Click for Photos
So much work as been completed since this project started… looking forward finishing up soon!
So much work as been completed since this project started… looking forward finishing up soon!
The windows are still being installed while some of the roofing material was delivered today ..
Everything’s taking shape… Go go go drywall soon to be delivered..
More work being completed by the trades.. looking ahead drywall will be coming soon..
The Brick wall on the rear of the building from the basement to the 4th floor has been completely demoed and the space has open up even that much better…
All the trades are moving in the right direction completing their contract scope.. The Embassy will soon have the elevator installed..
The window team are onsite installing windows in place while the steel stairs from the basement to the 4th floor are completed..
The platform for the elevator is installed ready for the Electrical and elevator soon to arrive..
Some great pictures show the hard work all trades have put fourth to start to give this great project closure..
Today not much rain fortunately, but the trades are making it happen.. much accomplished!!