6/12/18 Embassy of Rwanda Click for Photos
Today we had an meeting onsite regarding the new stairs that pocket into the elevator block wall going from top to bottom.. the measurements have been laid out for each section successfully..
Today we had an meeting onsite regarding the new stairs that pocket into the elevator block wall going from top to bottom.. the measurements have been laid out for each section successfully..
The plumbing ground work has been completed and inspected.. the footers have been inspected and the concrete has been poured in the basement..
The plumbing ground work is being roughed in the basement and the footer, plumbing inspection is scheduled this coming Monday..
Today the footers were dug out an formed in placed and tomorrow we have the inspection Scheduled before pouring of the concrete…
The removal of the brick niches are now complete… tomorrow the plumber and the Electrican will be onsite starting the Basement ground work..
The team is still moving in the right direction on completing the concrete scope and demoing the existing brick niches..
Today we’re removing the brick niches top to the bottom preparing for the new floor system..
The concrete block is being installed on the elevator shaft wall and tomorrow we will be removing the existing 1st floor joist system papering for the new floor joist..
The Brick crew are still removing existing brick, the others are digging footers in the basement soon to be poured..
Scaffold work being done today removing the brick at the niches and preparing for the new brick install…