7/11/18 Embassy of Rwanda Click for Photos
The plywood sub floor on the 2nd floor is completely installed.. the 3rd floor is getting prep for demo..
The plywood sub floor on the 2nd floor is completely installed.. the 3rd floor is getting prep for demo..
The 2nd floor joist are completed and the sub floor is being installed..This Thursday we plan on starting the 3rd floor demo..
The steel is complete and the joist are being installed on the 2nd floor and plywood subfloor will soon be installed..s..
The I beams are now installed on the 2nd floor and the joist installers now can erected the new floor in position.
The brick work off the scaffold is now complete up to the 3rd floor and the joist for the 2nd floor is soon ready for install..
The 3rd floor web joist system has been delivered, the steel beams on the 2nd floor are almost complete..
Today we had an man lift delivered to the site, this will help expedite a lot of the ground to upper floor movement during the joist and elevator shaft install..
The steel crew onsite working diligently today.. also the brick crew were working off the scaffold while the demo team were removing the remaining joist on the 2nd floor…
The Brick team were onsite today working off the scaffold.. the joist on the 2nd floor are almost demoed.. tomorrow we have the steel installed scheduled for the 2nd floor..
The new windows were delivered today, we are still removing joist and installing block on the 2nd floor for the elevator shaft wall..