Category: Embassy of Rwanda

Embassy of Rwanda

Posted on March 6, 2018April 4, 2018 by ECG Admin

E Construction is very excited to be working with the Republic of Rwanda in regentrifying their outdated historical building. Their Embassy is located at 1714 New Hampshire Avenue N.W Washington DC 20009. The project is scheduled to start early March 2018, and completing late November 2018. The facility will be equipped with a new 5 Read more about Embassy of Rwanda[…]

Posted in Embassy of RwandaLeave a comment

8/17/18 Embassy of Rwanda Click for Photos

Posted on August 19, 2018August 20, 2018 by Brian Ehardt

The exterior is being prep for paint and the trades are onsite roughing in before drywall..

Posted in Embassy of RwandaLeave a comment

8/16/18 Embassy of Rwanda Click for Photos

Posted on August 17, 2018August 20, 2018 by Brian Ehardt

The exterior of the building we’ve started the prep work on the brick and sanding of the fire escape metal.. before the primer can be applied…

Posted in Embassy of RwandaLeave a comment

8/15/18 Embassy of Rwanda Click for Photos

Posted on August 15, 2018August 20, 2018 by Brian Ehardt

The 4th floor is complete joist and plywood installed.. Now we have stairs install coming up from the basement..

Posted in Embassy of RwandaLeave a comment

8/14/18 Embassy of Rwanda Click for Photos

Posted on August 15, 2018August 20, 2018 by Brian Ehardt

The steel frames and stairs have been delivered and tomorrow the install will start..

Posted in Embassy of RwandaLeave a comment

8/13/18 Embassy of Rwanda Click for Photos

Posted on August 15, 2018August 20, 2018 by Brian Ehardt

Today we’re back onsite moving forward with the 4th floor joist and LVLs install .. also the steel crew are here installing their structural plates for the stairs..

Posted in Embassy of RwandaLeave a comment

8/01/18 Embassy of Rwanda Click for Photos

Posted on August 1, 2018August 3, 2018 by Brian Ehardt

Today the web joist were set on the barring wall for the 4th floor.. The Electrican is working on the lower floors roughing -in making his way to the top.. ibjhruzuya

Posted in Embassy of RwandaLeave a comment

7/31/18 Embassy of Rwanda Click for Photos

Posted on July 31, 2018August 3, 2018 by Brian Ehardt

Working our way up to the roof top, it won’t be long now before all trades will be onsite at same the time..

Posted in Embassy of RwandaLeave a comment

7/30/18 Embassy of Rwanda Click for Photos

Posted on July 30, 2018August 3, 2018 by Brian Ehardt

We have stock the 3rd floor with the new joist system that was delivered and stored in the fence area.. tomorrow the block crew will be onsite for the elevator shaft wall taking it to an new level..

Posted in Embassy of RwandaLeave a comment

7/27/18 Embassy of Rwanda Click for Photos

Posted on July 27, 2018August 3, 2018 by Brian Ehardt

The 4th floor is completely demoed, the bay window on the 2nd floor is getting prep for install… the team will be onsite tomorrow laying block and building barring walls for the 4th floor new joist install..

Posted in Embassy of RwandaLeave a comment

7/26/18 Embassy of Rwanda Click for Photos

Posted on July 26, 2018August 3, 2018 by Brian Ehardt

We have closed up the 3rd floor open stairwell to adequately demo the last of the existing floor joist on the 4th floor.. demo is almost complete.. with new web joist system installed..

Posted in Embassy of RwandaLeave a comment

Posts navigation

← Older posts

Archives

  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • November 2017

Meta

  • Log in

Like Us On Facebook

Hours & Info

161 Fort Evans Rd NE | Leesburg, VA 20176 | Suite 305
1-202-216-0077
info@ecggc.com
Monday - Friday
8AM-5PM
161 Fort Evans Rd NE Suite 305 | Leesburg VA, 20175
info@ecggc.com
(202) 216-0077
Zerif Lite developed by ThemeIsle