10/17/18 Embassy of Rwanda Click for Photos
More work is being completed moving forward, the pictures show how quickly it is..
More work is being completed moving forward, the pictures show how quickly it is..
The exterior is getting an new face lift and the siding team is working on the rear of the building, pump jacks in the air..
All close-in inspection have been achieved and the drywall can be hung complete.. the finishers can start stringing tape soon..
The team onsite are preforming very well.. committed to completing their work accomplishing the goal..
Had a good meeting today.. we are completing all trades scope finalizing all inspections..
The insulation and drywall is still being installed.. the roofer is almost complete.. and the painter has started prepping the exterior..
Drywall is in the air.. the drywall hangers are onsite hanging ceilings and walls.. it was good to see Moses onsite today walking him through the trades scope…
Tomorrow the insulation of the walls will start, the drywall will be hung shortly thereafter..
Moving in the right direction, keep on keeping on .. trades are fulfilling their scope..
The new windows are installed and the new exterior doors will also be installed soon..