8/16/18 Embassy of Rwanda Click for Photos
The exterior of the building we’ve started the prep work on the brick and sanding of the fire escape metal.. before the primer can be applied…
The exterior of the building we’ve started the prep work on the brick and sanding of the fire escape metal.. before the primer can be applied…
The 4th floor is complete joist and plywood installed.. Now we have stairs install coming up from the basement..
The steel frames and stairs have been delivered and tomorrow the install will start..
Today we’re back onsite moving forward with the 4th floor joist and LVLs install .. also the steel crew are here installing their structural plates for the stairs..
Today the web joist were set on the barring wall for the 4th floor.. The Electrican is working on the lower floors roughing -in making his way to the top.. ibjhruzuya