6/15/18 Embassy of Rwanda Click for Photos

Posted on June 15, 2018July 5, 2018 by Brian Ehardt

The basement concrete slab has been successfully poured… tomorrow the Carprnter crew will be onsite to frame up the bearing walls to accommodate the new floor joist system..

Posted in Embassy of RwandaLeave a comment

6/14/18 Embassy of Rwanda Click for photos

Posted on June 14, 2018June 15, 2018 by Brian Ehardt

Today we had the delivery of the LVLs and the new Web joist system for the 1st floor….Very excited we’re, tomorrow the concrete is schedule for the new basement slab..

Posted in Embassy of RwandaLeave a comment

6/13/18 Embassy of Rwanda Click for Photos

Posted on June 13, 2018June 14, 2018 by Brian Ehardt

With the ground work complete, the basement is being prep and the slab is schedule for concrete pour this coming Friday..

Posted in Embassy of RwandaLeave a comment

6/12/18 Embassy of Rwanda Click for Photos

Posted on June 12, 2018June 13, 2018 by Brian Ehardt

Today we had an meeting onsite regarding the new stairs that pocket into the elevator block wall going from top to bottom.. the measurements have been laid out for each section successfully..

Posted in Embassy of RwandaLeave a comment

6/11/18 Embassy of Rwanda Click for Photos

Posted on June 11, 2018June 12, 2018 by Brian Ehardt

The plumbing ground work has been completed and inspected.. the footers have been inspected and the concrete has been poured in the basement..

Posted in Embassy of RwandaLeave a comment

6/08/18 Embassy of Rwanda Click for Photos

Posted on June 8, 2018June 11, 2018 by Brian Ehardt

The plumbing ground work is being roughed in the basement and the footer, plumbing inspection is scheduled this coming Monday..

Posted in Embassy of RwandaLeave a comment

6/07/18 Embassy of Rwanda Click for Photos

Posted on June 7, 2018June 8, 2018 by Brian Ehardt

Today the footers were dug out an formed in placed and tomorrow we have the inspection Scheduled before pouring of the concrete…

Posted in Embassy of RwandaLeave a comment

6/06/18 Embassy of Rwanda Click for Photos

Posted on June 6, 2018June 7, 2018 by Brian Ehardt

The removal of the brick niches are now complete… tomorrow the plumber and the Electrican will be onsite starting the Basement ground work..

Posted in Embassy of RwandaLeave a comment

6/05/18 Embassy of Rwanda Click for Photos

Posted on June 5, 2018June 6, 2018 by Brian Ehardt

The team is still moving in the right direction on completing the concrete scope and demoing the existing brick niches..

Posted in Embassy of RwandaLeave a comment

6/04/18 Embassy of Rwanda Click for Photos

Posted on June 4, 2018June 6, 2018 by Brian Ehardt

Today we’re removing the brick niches top to the bottom preparing for the new floor system..

Posted in Embassy of RwandaLeave a comment

Posts navigation

← Older posts
Newer posts →

Archives

  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • November 2017

Meta

  • Log in

Like Us On Facebook

Like Us On Facebook

Hours & Info

161 Fort Evans Rd NE | Leesburg, VA 20176 | Suite 305
1-202-216-0077
info@ecggc.com
Monday - Friday
8AM-5PM
161 Fort Evans Rd NE Suite 305 | Leesburg VA, 20175
info@ecggc.com
(202) 216-0077
Zerif Lite developed by ThemeIsle