6/29/18 Embassy of Rwanda Click for Photos
The steel crew onsite working diligently today.. also the brick crew were working off the scaffold while the demo team were removing the remaining joist on the 2nd floor…
The steel crew onsite working diligently today.. also the brick crew were working off the scaffold while the demo team were removing the remaining joist on the 2nd floor…
The Brick team were onsite today working off the scaffold.. the joist on the 2nd floor are almost demoed.. tomorrow we have the steel installed scheduled for the 2nd floor..
The new windows were delivered today, we are still removing joist and installing block on the 2nd floor for the elevator shaft wall..
Another day on the 2nd floor removing the existing floor joist and framing of the barring walls to accommodate the new floor..
Working on the 2nd floor removing the old Joist and getting ready to start framing the barring wall to support the floor above.. Going up the tower!
The 1st floor and the basement are shaping up with an new look, todays engineer web joist and plywood are installed.. Masons are back onsite working on the elevator shaft wall..
The new web joist floor system is going well, later today will be installing plywood on the joist.. Tomorrow the brick team will be back onsite demo and laying of the brick off the scaffolded set outside of building..
The joist are being installed, the I beams are being set, the ducts for the basement are being connected.. things are looking good..
Tomorrow, the new Web joist system crew will be onsite, installing the LVLs and the new joist system… we will start the install from front to back of the Embassy..
The barring walls are being built to support the joist install.. the joist will be installed soon going up the tower..