5/31/18 Embassy of Rwanda Click for Photos

Posted on May 31, 2018June 1, 2018 by Brian Ehardt

The Brick crew are still removing existing brick, the others are digging footers in the basement soon to be poured..

Posted in Embassy of RwandaLeave a comment

5/30/18 Embassy of Rwanda Click for Photos

Posted on May 30, 2018June 6, 2018 by Brian Ehardt

Scaffold work being done today removing the brick at the niches and preparing for the new brick install…

Posted in Embassy of RwandaLeave a comment

5/29/18 Embassy of Rwanda Click for Photos

Posted on May 29, 2018May 30, 2018 by Brian Ehardt

The concrete team is back in the basement and the Elevator pit is taking shape.. block laying soon will take place before the floor Joist are delivered..

Posted in Embassy of RwandaLeave a comment

5/28/18 Embassy of Rwanda Click for Photos

Posted on May 28, 2018May 29, 2018 by Brian Ehardt

Today on Memorial Day, the concrete crew took the day off while the carpenter crew was onsite and started removing the 1st floor stairs and existing floor joist..

Posted in Embassy of RwandaLeave a comment

5/25/18 Embassy of Rwanda Click for Photos

Posted on May 25, 2018May 29, 2018 by Brian Ehardt

Lots of hard work has gone into this great project already.. these picture show scaffolding complete, getting ready for the exterior brick work.. inside elevator pit steal rebar installed for shaft wall form work to commence..

Posted in Embassy of RwandaLeave a comment

5/24/18 Embassy of Rwanda Click for Photos

Posted on May 24, 2018May 25, 2018 by Brian Ehardt

Today the crock for the sump pump at the elevator pit was installed and inspection was approved and concrete poured..

Posted in Embassy of RwandaLeave a comment

5/23/18 Embassy of Rwanda Click for Photos

Posted on May 24, 2018May 25, 2018 by Brian Ehardt

The team is still in the basement getting their soil and concrete inspection moving forward..

Posted in Embassy of RwandaLeave a comment

5/22/18 Embassy of Rwanda Click for Photos

Posted on May 22, 2018May 25, 2018 by Brian Ehardt

The underpinning scope for the elevator pit has been inspected and concrete poured.. now moving forward to the pad and footers.

Posted in Embassy of RwandaLeave a comment

5/21/18 Embassy of Rwanda Click for Photos

Posted on May 21, 2018May 25, 2018 by Brian Ehardt

Concrete truck was onsite today after the inspection was completed on the elevator pad.. now prepping for the footers and structural pier connection..

Posted in Embassy of RwandaLeave a comment

5/18/18 Embassy of Rwanda Click for Photos

Posted on May 18, 2018May 21, 2018 by Brian Ehardt

Still moving forward with the work in the basement.. Monday we have inspection on the elevator pad scheduled and pouring of concrete..

Posted in Embassy of RwandaLeave a comment

Posts navigation

← Older posts

Archives

  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • November 2017

Meta

  • Log in

Like Us On Facebook

Like Us On Facebook

Hours & Info

161 Fort Evans Rd NE | Leesburg, VA 20176 | Suite 305
1-202-216-0077
info@ecggc.com
Monday - Friday
8AM-5PM
161 Fort Evans Rd NE Suite 305 | Leesburg VA, 20175
info@ecggc.com
(202) 216-0077
Zerif Lite developed by ThemeIsle